The first equipments left Sedan come finally in the port of Umm Said, to join the unit of preparation of household refuse and energy valuation of Doha, in QATAR.
Since the middle of December, already 80 containers of 6 Aspiro-tri ®, 6 optical separators, 7 magnetic separators, 6 separators of non-ferrous, about sixty conveyors, platforms of sorting and 1 press took the sea; and 30 others will leave still in the next few weeks.
From Marseille and Antwerp the shipping sets between 2 and 4 months following the harbour traffic. The delivery deadlines require an organization and a rigorous follow-up. As far as since last March 16th the assembly started too.
Other specificity of the construction site and not the slightest, the climatic conditions: the unit which the surface will reach more than 250 hectares builds itself in full desert where the average temperature from May to September is 35 ° (in the shade!), with peaks in 52 °, in summer.
Equipments will thus be subjected to hard test. Engines for example answer particular standards: climate sealed engines, classify H. The painting required a complex finish, the cabin and also all the electric cupboards are equipped with an air conditioning answering very binding requirements.
But beyond these technical constraints, the unit of Doha, will be a original realization; because the process which will allow to produce a compost from raw household refuse, also privileges the recovery of all the recyclable products such as: paper, steel, non-ferrous and plastics parts, reducing at most the refusals to bury.
|
 more than 250 hectares builds itself in full desert
|